Should I repair my dock or rebuild it?
Check the pilings first. If only a few piles are soft at the waterline, repair wins: swap those at $2,000 to $3,500 each and redeck if the frame is worn out. Once piles are failing in a row, or a storm knocked the frame off them, a same-footprint rebuild at $25,000 to $50,000 makes more sense than patching. It also keeps the state's size-for-size exemption in play.
Does dock repair in Pasco County need a permit?
In unincorporated Pasco, yes. Code Sec. 18-36 requires a permit for any dock repair or alteration, and the land development code counts new or replacement supports as an improvement. Inside the City of Port Richey, minor repairs need no permit. New Port Richey permits alterations through the city. We confirm the right desk for your address on the first visit.
Can I just replace deck boards on my Palm Harbor dock without a permit?
From Pinellas Water & Navigation, yes. Code Sec. 58-544 says replacing deck boards alone needs no Water and Navigation permit. That exemption ends at the boards, though. Stringers, caps and floats aren't covered, so a reframe needs the permit, and the repair fee for a previously permitted dock is $560 on the schedule effective Oct. 1, 2026.
How long do I have to fix a dock a hurricane knocked out?
Get moving within the year. The state rule behind the repair exemption covers a dock that still works, or one made non-functional within the last year by a single event such as a storm. In Port Richey, a city notice about an unsafe dock starts a 15-day clock to begin repairs, and one that became a navigation hazard gets 48 hours.
Do I need a Notice of Commencement for a dock repair?
If the contract is over $2,500, Florida law (F.S. 713.13 with 713.02(5)) has the owner record a Notice of Commencement before work starts. Over $5,000, the permit office also needs a copy before the first inspection. Pasco's own owner-builder sheet lists the notice for projects over $5,000. If work doesn't start within 90 days of recording, the notice is void.
What happens to the old pilings when you replace them?
They come out, every one of them. Oldsmar's code requires the whole old piling to be pulled, including the part below the waterline, when one gets replaced. Then the treated wood heads to a permitted landfill. In Pinellas, CCA-treated piles go to a permitted landfill by appointment, cut to 4 feet or less and stripped of hardware, with a $110 handling fee per load on top of the disposal fee.
Can you repair the dock and the boat lift on the same visit?
Yes, and handling both at once saves a second trip with the equipment. Lift piles get the same check as dock piles. Pasco wants a separate permit for each in-water structure, so the dock and the lift get filed separately, and rewiring a lift carries its own electrical permit, which runs $3,000 to $5,000 in our range. Our boat lift page covers sizing and lift costs.